title
Noise Ordinance - Late Night Foundation Pours
SCP Macedonia
2830 Macedonia Rd
MIT
MIT Supported - Mark All Applicable
☐ Critical Staffing Needs (staffing shortages, retention)
☐ Financial Stability/Sustainability (diverse tax base)
☐ Safety & Protecting Community (code enforcement, stormwater)
☐ Commercial Development
☐ Downtown Development
☐ Tourism (increase share; museum should equitably represent community; events)
☐ Downtown Parking (address parking needs)
☐ Youth Program/Council (community center for youth and seniors; learning gap)
☐ Prepare for Growth and Development (infrastructure in place; annexation; curb cuts; recycling, signage)
Staff Notes
Section 10-53 of the Code of Ordinances provides the following:
The operation of motorized construction equipment and the performance of outdoor
construction and/or demolition activity on any building, structure, road or project shall be prohibited during the following times: Monday through Saturday from 6:00 p.m. until 7:00 a.m. during Eastern Standard Time and from 7:00 p.m. until 7:00 a.m. during Eastern Daylight Time, and all day Sunday. This provision shall not apply if the noise control administrator determines that the loss or inconvenience that would result to any party in interest is of such a nature as to warrant special consideration. In such cases, the noise control administrator may grant a renewable permit for a period not to exceed ten (10) days for this work to be done, but in no case shall any such work contemplated herein be performed between the hours of 10:00 p.m. and 7:00 a.m.
Fansler Construction is requesting an Early Work Variance to start pouring the larger concrete building slabs early in the morning for the SCP Macedonia Multi-Family Project located at 2830 Macedonia Road SW, Powder Springs, GA. They are requesting to pour the following building slabs starting at 2AM on the following tentative dates (please see attached site plan noting the slabs to be poured and pour dates in red):
• Building 1000: September 25th, 2024
• Building 2000: October 7th, 2024
• Building 4000: October 8th, 2024
• Building 5000: October 14th, 2024
• Clubhouse: October 14th, 2024
• Maintenance Building and Car Wash: October 16th, 2024
• Building 3000: October 18th, 2024
• Building 6000: October 25th, 2024
• Building 8000: October 24th, 2024
• Building 7000: October 30th, 2024
• Building 9000: November 5th, 2024
Since the site is a large site in a wooded area with few neighbors in the immediate vicinity, they are willing to contact neighborhoods within a ¼ mile radius of the site.
The noise/lighting activities during the early hours will be limited to using lights to light up slab areas, concrete trucks to deliver concrete and concrete boom pump trucks to pump out the concrete into the slab forms.