Action Summary:
title
Final Plat - Fairhaven at Preston
MIT
MIT Supported - Mark All Applicable
☐ Critical Staffing Needs (staffing shortages, retention)
☐ Financial Stability/Sustainability (diverse tax base)
☐ Safety & Protecting Community (code enforcement, stormwater)
☐ Commercial Development
☐ Downtown Development
☐ Tourism (increase share; museum should equitably represent community; events)
☐ Downtown Parking (address parking needs)
☐ Youth Program/Council (community center for youth and seniors; learning gap)
☐ Prepare for Growth and Development (infrastructure in place; annexation; curb cuts; recycling, signage)
staffnotes
Staff Notes
The rezoning for this development was approved on April 5, 2021 and allowed for 34 townhouse units (Powder Spring East Project). The land disturbance permit was issued on May 20, 2022 (Preston East). The next stage of development is the approval and the recording of the final plat. Once the final plat is approved and recorded, building construction can begin.
Staff recommends that the final plat be approved with the following conditions.
1) Receipt of all subdivision improvement guarantees, including proof of payment for street lights.
2) Approval of as-built of completed infrastructure, detention pond certifications and stormwater maintenance agreement.
3) Any outstanding staff comments are addressed to meet the requirements of the Unified Development Code.
4) Completion of review by City Attorney.